How do you prepare capacity before a PI Planning?

Before a PI Planning, each team must know its net capacity for every iteration of the PI: available days, absences, run share, and shared people. The RTE consolidates these figures to detect conflicts between teams and ensure that commitments made during the event stay sustainable.

PI Planning: preparing capacity before the event

A successful PI Planning is prepared with capacity figures that are already consolidated.

Last updated :

Preparation checklist

  • Collect absences and events for the next two or three months.
  • Compute each team's capacity per iteration.
  • Identify shared people and split their time.
  • Reserve the run, innovation, and planning share.
  • Spot cross-team dependencies in advance.

During and after the event

  • Compare commitments with the capacity displayed in the session.
  • Adjust commitments that exceed capacity rather than assuming overtime.
  • Track capacity consumed over the PI and correct if needed.

FAQ

Who prepares capacity?

Each team enters its availability; the RTE consolidates across the train.

What if commitments exceed capacity?

Reduce scope, postpone items, or adjust capacity, but do not assume overtime.

How long is a PI?

Often 8 to 12 weeks, meaning four to six iterations.